On Monday, Nov. 23, the Augusta-Richmond County Planning Commission holds a public hearing on rezoning and special exception petitions for what Georgia state filings describe as a 600-megawatt data center campus in south Augusta, Georgia. The applicant is 3 G Investments, LLC, acting on behalf of The Nixon Trusts. It is asking the city to rezone the land for the Nixon Technology Center and to grant a special exception for it. The site sits off Four H Club Road and Mike Padgett Highway, near Augusta Regional Airport.
The hearing comes after the Georgia Department of Community Affairs (DCA) listed the project's regional review as completed. It also falls in the weeks after the Augusta Commission adopted a data center ordinance on two 6-5 votes this fall.
What Is Being Proposed
The project's Development of Regional Impact (DRI) filing with the DCA is tracked as DRI #4853. The initial form, completed by Augusta/Richmond planning staff, describes a proposed 3.34 million-square-foot data center campus on one parcel of about 388 acres in southeast Richmond County. The listed addresses are 1550 and 1538 Four H Club Road and 3806 Mike Padgett Highway. The form names 3 G Investments, LLC of Woodbridge, Virginia, as developer and The Nixon Trusts as owner. It lists rezoning among the actions requested of the local government and gives 2028 and 2029 as the estimated completion dates for the phase and 2029 for the overall project. Construction Review Online, in an Oct. 14 report on the DRI filing, put the campus at 3.3 million square feet.
WRDW/WAGT describes the site as about 383 acres. Its Nov. 17 report says the application calls for seven buildings, each at least 500 feet from existing residential properties. The station also reported that the land is near Augusta Regional Airport, borders the Castle Pines Mobile Home Park and lies in Commission District 1.
The two petitions on Monday's agenda, as WRDW reported them:
- Z-26-18: rezoning the land from agricultural, general business and heavy industrial zoning to the DC (data center) district.
- SE-26-22: a special exception to establish a data center.
WRDW reported that the developer filed its applications Sept. 28. The hearing was first scheduled for Nov. 2, then moved to Dec. 7, and is now a special called meeting on Nov. 23, according to the station.
Power, Water and Money: What the Filings Say
Power. WRDW reports that the DRI form lists a peak electrical load of 600 megawatts (MW), with Georgia Power as the provider. According to WRDW, the form says a study "has been requested from the energy supplier" on whether existing power infrastructure is sufficient. WRDW also cited a draft fiscal analysis by the consulting firm MuniCap Inc. that assumes the campus runs at 80% of its 600-MW capacity, or about 4.2 billion kilowatt-hours a year. That figure is consistent with the arithmetic: 600 MW x 0.8 x 8,760 hours is about 4.2 billion kWh.
Water. WRDW reports that the DRI form describes the cooling system as closed loop and says "once the system is charged, there will be no daily impact." The station noted that the form does not say how much water the initial fill would require. These are the applicant's own statements on a state form, as relayed by WRDW. They are not findings by the utility or the city. WRDW also reported that Augusta's data center ordinance requires closed-loop or air-cooled cooling.
Value, taxes and jobs. According to WRDW, the DRI form estimates the campus would be worth $3 billion at build-out, would generate $38.8 million a year in local tax revenue and would employ 40 full-time workers. WRDW added that the MuniCap draft analysis, dated Sept. 22, projects about 571 direct full-time-equivalent jobs and that it is not clear why the two job figures differ.
Noise, Water and Power Studies and the Agenda
WRDW asked Augusta's planning director whether the developer has submitted technical studies on noise, water use and electricity. She wrote that "That is a requirement when the applicant submits for a Site Development Application," according to the station. A site development application is a separate filing from the rezoning and special exception requests before the Planning Commission on Monday. WRDW reported that she did not say whether any such studies have been submitted or whether the city has received a study from Georgia Power.
WRDW also reported that the Augusta Commission approved the data center ordinance on first reading Sept. 15 and on second reading Oct. 6, both times on 6-5 votes. The Nixon applications were filed Sept. 28, between those two votes. The planning director wrote that the applicant "chose to follow the September 9th D-C District zoning requirements approved by the governing body." According to WRDW, she did not say when the ordinance took legal effect or how it treats applications filed between the two votes.
Where the Regional Review Stands
A Development of Regional Impact review is a look at the effects large projects could have beyond their own property, WRDW explained. The DCA application summary for DRI #4853 shows this timeline:
- Oct. 12, 2026: initial form submitted
- Oct. 19, 2026: additional DRI information form submitted
- Oct. 30, 2026: determination that the project "warrants regional review," completeness certification and request for comments
- Nov. 18, 2026: finding by the Central Savannah River Area Regional Commission (RDC)
- Nov. 29, 2026: projected process completion
The DCA summary lists the review's current status as Completed, and it still shows Nov. 29 as the projected completion date. The summary record does not describe what the regional commission's finding says.
What Happens Next
The Augusta-Richmond County Planning Commission will hear Z-26-18 and SE-26-22 at 2 p.m. Monday, Nov. 23. WRDW's Nov. 18 report places the meeting in the Augusta Commission Chambers. Its Nov. 17 report listed Room 260 of the Augusta Municipal Building, 535 Telfair St. Anyone planning to attend should check the location with the city.
The Planning Commission only makes a recommendation. According to WRDW, the final decision belongs to the Augusta Commission, which has the authority to approve, deny or table zoning matters. WRDW reported that written or verbal comments can be submitted to the Augusta Planning and Development Department at (706) 821-1796 during regular business hours. The DCA lists Nov. 29 as the projected completion date for the regional review.
Sources
- Georgia DCA Development of Regional Impact, DRI #4853 Application Summary (Nixon Technology Center)
- Georgia DCA DRI #4853 Initial DRI Information Form
- Key questions remain ahead of public hearing on proposed South Augusta data center - WRDW/WAGT (published Nov. 18, 2026)
- Planning Commission to hear 383-acre data center proposal in south Augusta - WRDW/WAGT (Nov. 17, 2026)
- Application Filed for 3.3 Million Sq. Ft. Nixon Technology Data Center Campus in Augusta - Construction Review Online