The Cameron County Commissioners Court in Texas voted 3-2 on Tuesday, Nov. 17, against a procedural step that would have started the county's formal review of a property tax abatement for Space Exploration Technologies Corporation (SpaceX). The company has proposed a data center and power plant at its Starbase complex east of Brownsville.

The vote was on Item 4.H of the court's regular meeting agenda: "Consideration and authorization to post a notice of intent to consider a Chapter 312 tax abatement agreement with Space Exploration Technologies Corporation and authorize the Cameron County Judge to sign the notice (RA-Economic Development)." The Rio Grande Guardian describes the outcome as the court voting not to advance a public hearing on a county property tax abatement for the project. Because the notice was not authorized, no county abatement hearing is now scheduled, according to the reports below.

The decision covers only the county. SpaceX has also applied for a separate abatement from the City of Starbase, and the Rio Grande Guardian reports that the city will hold a public hearing on it Dec. 9, 2026.

How the Vote Broke Down

The agenda lists five members of the Commissioners Court: County Judge Eddie Treviño Jr. and Commissioners Sofia C. Benavides (Precinct 1), Joey Lopez (Precinct 2), David A. Garza (Precinct 3) and Gus Ruiz (Precinct 4). The meeting was scheduled for 9:30 a.m. in the courtroom of the Oscar C. Dancy Building, 1100 E. Monroe St., in Brownsville.

Both Newsweek and the Rio Grande Guardian report that Treviño and Lopez voted in favor of advancing the item. With the vote 3-2 against, the other three members of the court, Benavides, Garza and Ruiz, made up the majority. Newsweek describes the request as a 100% property tax abatement lasting 10 years.

Newsweek reported that Lopez, one of the two members who voted yes, told KRGV: "I felt that we needed to go ahead and review numbers so that we had all the facts and figures." Newsweek also quoted him as saying "there won't be a second meeting" and "So the [request] is dead."

The agenda also included an executive session item, 6.C, to confer with legal counsel on legal issues involving potential economic development incentives. The agenda itself gives no project cost or acreage.

What SpaceX Proposed

Published reports agree on the site but give different cost figures, and each figure below is attributed to the outlet that reported it.

Site. Newsweek and the Rio Grande Guardian both put the site at 444 acres. Newsweek places it in the Starbase complex, about 20 miles east of Brownsville, inside the county's Enterprise Zone. The Rio Grande Guardian reports that the City of Brownsville disannexed the land in August and the City of Starbase annexed it in September.

Cost. Newsweek describes the project as a $24 billion data center and natural gas power plant, and says $24 billion is the expected investment for the initial phase, according to a public hearing notice; it adds that the project could include future expansions. The Rio Grande Guardian refers to a proposed $17.9 billion facility. It also quotes one speaker at the meeting as saying SpaceX has said it will spend $26 billion.

Tax impact and jobs. The Rio Grande Guardian reports that a tax break on the facility could cost the county an estimated $5.2 billion in forgone property tax revenue while creating about 500 permanent jobs. It attributes those estimates to an opponent who cited them at the meeting rather than to the county or SpaceX.

Application timeline. According to the Rio Grande Guardian, SpaceX originally submitted its county abatement application on Oct. 15, 2026, and filed a revised application on Nov. 9, 2026, eight days before the vote.

The Power Plant and the State Permit

The county vote came one day after a state air permit decision on the project's generation. Newsweek, citing POLITICO, reports that the Texas Commission on Environmental Quality (TCEQ) granted an air pollution permit on Monday, Nov. 16. According to that report, the permit covers 35 natural gas-burning turbines producing 750 MW and allows up to 248 tons per year of nitrogen oxides (NOx) emissions.

The state's handling of data center permits has also changed in recent months. Newsweek reports that in September, Gov. Greg Abbott ordered TCEQ to pause data center permits while the Electric Reliability Council of Texas (ERCOT) gathered information on their grid impact. Newsweek says TCEQ later said ERCOT had finished and that it had resumed normal permit review. Newsweek also reports that Governor-elect Gina Hinojosa pledged during her campaign to halt data center approvals until "real protections" are in place for Texans.

A county tax abatement and a state air permit are separate approvals. The Commissioners Court vote concerned only whether the county would take up an abatement of the project's county property taxes. Neither source presents it as a decision on whether the facility can be built or operated.

Public Comment

The Rio Grande Guardian reports that more than a dozen speakers voiced unanimous opposition to the abatement at the meeting, including residents, environmental advocates, faith leaders and local officials. Opponents argued that SpaceX is already established in the county and is building on the 444-acre site, so an abatement would not recruit new industry. Other speakers raised concerns about air quality, water supplies during drought, traffic, flood control and gentrification. DataCenterFeed does not name private residents who speak during public comment.

Why the Notice Step Matters

Item 4.H asked only for permission to post a notice of intent to consider a Chapter 312 abatement agreement and to have the county judge sign that notice. It did not ask the court to approve an abatement agreement. Because the court voted the item down, no county hearing on the abatement is scheduled, and no agreement was before the court.

The county and the City of Starbase are acting on separate applications. According to the Rio Grande Guardian, SpaceX has applied separately to the city, and the county's decision does not by itself change the city's scheduled hearing.

What Happens Next

No Cameron County abatement hearing is scheduled after the 3-2 vote. Commissioner Lopez was quoted by Newsweek as saying "there won't be a second meeting."

The next scheduled public step is at the city level. The Rio Grande Guardian reports that the City of Starbase will hold a public hearing on Dec. 9, 2026, on SpaceX's separate application for a city tax abatement.