PJM Interconnection has given federal regulators its answer on data centers. On Monday, Nov. 16, PJM filed two separate packages at the Federal Energy Regulatory Commission. One would change how large loads and new generation get studied and connected. The other would set technical performance rules for the biggest computing facilities on its system. According to Utility Dive, most major U.S. grid operators filed the same day, all responding to show-cause orders FERC issued in June.
The filings matter to anyone tracking a proposed campus. They bear on how fast a large load can get grid service, who pays for the transmission upgrades it triggers, and what a data center has to do electrically to stay connected when the grid has a problem.
Why FERC Asked
According to Utility Dive, FERC's June show-cause orders directed grid operators to address five issues: efficient transmission service application and study processes, preventing cost shifts and providing transparency into transmission costs, co-location and behind-the-meter generation, new transmission services for flexible large loads, and a study process for generating facilities that serve "electrically proximate" large loads and co-located loads.
PJM's Inside Lines newsroom said its interconnection filing tracks FERC directives in two parallel dockets, one on large load and one on co-located load. Utility Dive reported that PJM's transmission owners also filed their own tariffs covering co-located and large loads.
Fast Energization: One Study Cycle Instead of Two
The centerpiece of PJM's first filing is a process it calls Fast Energization. PJM's Inside Lines newsroom says it would cut the projected study timeline from two years to one by studying generation and large-load requests together instead of in separate, duplicative processes. Utility Dive, citing PJM, reported that the single one-year process would be about twice as fast as the current process. Utility Dive also quoted PJM's Donald Bielak, director of interconnection planning, who told FERC in a separate filing that it marks "the next evolution of PJM's interconnection process."
The proposal includes several other changes, as PJM describes them:
- Earlier readiness and financial requirements. PJM would make these requirements stricter and apply them earlier in the process. PJM says the goal is to limit projects to those that are truly ready to build.
- New transmission services for large loads. PJM says the process establishes new transmission services for data centers and other large loads, including loads with their own generation and flexible loads that can reduce the load they require. PJM's description notes that FERC found new services should reflect loads willing to limit their use of the system, including an interim service while network upgrades are constructed.
- Cost transparency for states. PJM says the package would give states transparent access to the costs of transmission improvements driven by data centers, as directed by FERC.
The November filing follows large-load proposals PJM made this summer. Data Center Frontier reported at the time that the earlier plan included an Interim Resource Adequacy Service, under which new large loads that do not bring their own new capacity, and are not covered through the Reliability Backstop Procurement, could face curtailment during capacity shortages. It also included a Bring Your Own Capacity option and an expedited generation track. Data Center Frontier reported that the proposed backstop procurement aims to fill a 6,831 MW shortfall identified for the 2028/2029 delivery year. The Nov. 16 filings are separate from that framework.
The Ride-Through Filing and the July 22 Event
PJM's second filing deals with how data centers behave during grid disturbances. It seeks to define a new category called Large Computational Load (LCL), which PJM defines as 50 MW or greater. The filing would require current and future LCLs to meet voltage and frequency ride-through requirements, meaning they would have to remain connected to the grid during transmission disturbances rather than switching to backup generation.
PJM ties the proposal to a specific event. According to PJM's announcement, on July 22 nearly 3.9 GW of data centers unexpectedly transferred from utility power to their own onsite generators in response to a routine transmission disturbance. PJM called it the largest such load transfer in its history. PJM said such events affected system voltages, frequency, power flows and generator behavior in the Dominion transmission zone and across the Eastern Interconnection, and that its Control Center managed the event safely.
PJM's numbers show why it considers the issue pressing. The grid operator says it already serves around 10 GW of existing LCL and forecasts additions of up to 30 GW by 2030.
The proposed requirements would take effect Jan. 16, 2027, and would apply to both new and existing facilities, on different schedules:
- New LCLs would have to demonstrate compliance as a condition of interconnection and operation.
- Existing LCLs would have to achieve compliance within one year of the effective date or within one year of commercial operation, whichever is later.
How the Other Grid Operators Responded
PJM was not alone. Utility Dive reported that the proposals were filed Monday, Nov. 16, except ISO New England's, which was filed the previous Friday, and that the Southwest Power Pool is slated to file by this Friday. Based on Utility Dive's reporting, the proposals differ by region:
- MISO proposed a Large Load Project Review process and new transmission service options, plus, in a separate filing, a Grid Responsive Integration Transmission Service for large loads that can limit their electric use under certain price and reliability conditions.
- CAISO proposed standardized application information, deposits and milestones for large loads, along with new service options for flexible large loads that can cut their electric use when transmission capability is unavailable.
- NYISO proposed Firm Withdrawal Service and Non-Firm Withdrawal Service, and a State Exempt Load Project exception to its resource adequacy approach.
- ISO-NE proposed maintaining on its website a list of the network upgrades identified for each large load, with cost estimates, and said it plans to require large loads to bring their own new capacity. Utility Dive reported that ISO-NE plans to work with stakeholders on the details, with a goal of filing a proposal at FERC later this year.
Several of the filings share similar building blocks: service options for flexible loads, standardized milestones and deposits or earlier readiness requirements, and public disclosure of upgrade costs. Those features align with the cost-shift and flexible-load issues FERC listed in June.
What It Means for Communities and Developers
For local officials and residents, the cost-transparency pieces are the most directly relevant. PJM says its filing would give states transparent access to data-center-driven transmission upgrade costs, and ISO-NE proposes publishing upgrade costs for each large load on its website.
For developers, the proposals add obligations along with the speed. PJM's stricter, earlier readiness requirements would require projects to commit sooner. A facility of 50 MW or more in PJM would also have to demonstrate ride-through compliance as a condition of interconnection, or within the compliance window if it is already operating.
None of these proposals is in effect yet. Each one needs FERC action, and the commission can accept, reject or modify them.
What Happens Next
PJM asked FERC to set a 60-day comment period on its Fast Energization filing and to issue an order within 120 days, according to PJM. The ride-through filing proposes an effective date of Jan. 16, 2027. Utility Dive reported that SPP is slated to file its proposal by Friday.
Sources
- PJM Plan Would Cut Interconnection Process Time in Half (PJM Inside Lines)
- PJM Proposes New Rules to Protect Grid Reliability as Data Center Demand Grows (PJM Inside Lines)
- Grid operators file closely watched large load interconnection reforms at FERC (Utility Dive)
- PJM's New Data Center Power Equation (Data Center Frontier)