The Texas Commission on Environmental Quality (TCEQ) has resumed its normal review of permit applications from data centers. The freeze that Gov. Greg Abbott ordered in September is over, even though the grid operator's full audit findings have not yet been released. Within days of the restart, the agency issued an air permit to SpaceX for a data center and natural gas power plant in the Rio Grande Valley.

The sequence matters for developers, utilities and the communities where campuses are proposed. The pause was tied to the Electric Reliability Council of Texas (ERCOT) completing an audit. Permitting has now restarted because ERCOT has finished gathering information. Its findings are scheduled for later.

How the Pause Began

Abbott's office announced the directive on Sept. 21. It ordered TCEQ to halt all permits sought by data centers until ERCOT completed its audit. The governor's office also said no state agency should move forward with approvals until that information had been acquired. TCEQ was told to update the governor's office by Oct. 19, 2026. In the same announcement, Abbott said he would work with the Legislature next session to eliminate financial incentives for data centers.

The directive did not set a fixed end date for the freeze. It tied the restart of approvals to ERCOT's work.

Why Permitting Restarted

According to the Texas Tribune, TCEQ received notice on Friday, Nov. 13, from Abbott's office that ERCOT had completed gathering information on community impacts. TCEQ spokesperson Laura Lopez told the Tribune: "The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations."

The Hill described the move as TCEQ resuming data center permit reviews after the pause by Abbott, whom it called the outgoing governor.

The governor's notice and ERCOT's audit findings are separate steps. According to Shattered, an ERCOT spokesperson said the grid operator plans to release its audit findings on Dec. 10, 2026. That means applications are moving through TCEQ again before the audit results that originally triggered the freeze are public.

The SpaceX Permit

The first high-profile approval after the restart went to SpaceX. Shattered, citing reporting by Reuters, Politico and the Texas Tribune, reported that TCEQ issued SpaceX an air permit on Nov. 16, 2026, for a data center and gas-fired power plant in the Rio Grande Valley. According to that reporting:

  • The plant would use 35 gas turbines with a combined 750 megawatts.
  • The site covers 444 acres.
  • The permit allows up to 248 tons per year of nitrogen oxides (NOx).
  • The facility is planned to run off-grid.

An off-grid design is relevant to the ERCOT question at the center of the pause. A campus that makes its own power does not draw from the ERCOT system in the way a grid-connected load would. It still needs an air permit for its on-site generation, and that permit is what TCEQ issued. The sources reviewed do not say whether the SpaceX application was among those held during the freeze.

Reaction

Public Citizen criticized the resumption. Kathryn Guerra of the advocacy group called for TCEQ's commissioners to resign, the Texas Tribune reported.

The decision also comes during a change in state leadership. The Hill reported that Gov.-elect Gina Hinojosa has vowed to protect Texans from data center projects, and the Texas Tribune reported that on the campaign trail she vowed to keep data center approvals paused until legislators pass new state laws. Abbott's own September announcement said he would seek to eliminate state financial incentives for data centers in the next legislative session. The sources reviewed do not give details of specific legislation or executive action from the incoming administration.

What It Means for Pending Projects

For developers, the practical change is that TCEQ is again processing data center applications, including air permits for on-site generation, under its standard rules. Lopez's statement does not describe any new data-center-specific criteria. The agency said it will evaluate applications "under all applicable state and federal laws and regulations."

For local officials and residents near proposed sites, the SpaceX permit shows the scale of some on-site generation now going through review: hundreds of megawatts of gas turbines with permitted NOx emissions in the hundreds of tons per year, according to the figures Shattered reported. Abbott's September directive also covered approvals by other state agencies. The sources reviewed do not say whether those agencies have formally resumed their own reviews.

What Happens Next

According to an ERCOT spokesperson quoted by Shattered, ERCOT plans to release its audit findings on Dec. 10, 2026. Separately, Abbott's office said he will work with the Legislature next session to eliminate financial incentives for data centers. Gov.-elect Hinojosa takes office after Abbott, and The Hill reported she has vowed to protect Texans from data center projects. The Texas Tribune also reported that ERCOT plans to discuss its findings at the next Public Utility Commission open meeting on Dec. 17. Meanwhile, TCEQ says it is evaluating pending data center applications under its normal process.