The North Carolina Utilities Commission ruled on Duke Energy's two Carolinas rate cases on Nov. 16, 2026, and it did not approve the Stipulation of Settlement on Large Load Tariff that Duke, the Public Staff and other parties had filed in October. According to Duke Energy's Form 8-K, the commission's written orders for Duke Energy Carolinas (DEC) and Duke Energy Progress (DEP) approved the comprehensive revenue requirement settlements. The orders also "establish a DC Schedule applicable to certain data center customers."

Duke's filing gives no further detail on the schedule in its main text, saying only: "We are still assessing that portion of the Orders." The terms are set out in an attached DEC fact sheet, filed as Exhibit 99.1 for Docket E-7 Sub 1329. It shows the commission approved the comprehensive settlement and all other rate case stipulations without modification, except the Stipulation of Settlement on Large Load Tariff filed Oct. 6, 2026 by DEC, DEP, the Public Staff and other intervening parties. The fact sheet says the DC Schedule includes some terms from that settlement and others that are incremental.

What the DC Schedule requires

The Exhibit 99.1 fact sheet lists the schedule's requirements:

  • Contract length: minimum 15-year contract terms for data centers over 100 MW.
  • Minimum bill: minimum billing demand of 75% of contract demand. A customer pays for at least three-quarters of the capacity it contracted for, even if it uses less.
  • Curtailment: interim curtailment provisions.
  • Dedicated facilities: contribution in aid of construction for facilities dedicated to the customer.
  • Transmission: a letter of credit covering all transmission network upgrades, plus partial direct assignment of transmission upgrade costs based on customer benefit. The fact sheet says that methodology is still to be determined.
  • Early exit: liquidated damages for early termination.
  • Generation: a stranded generation charge. It requires the customer to post security and make an additional payment at the end of the contract term, under a methodology the fact sheet also lists as to be determined.

Two of these items, transmission cost assignment and the stranded generation charge, are still unfinished. The orders set the structure, but the formulas that turn it into dollar amounts for a given campus have not been written.

How it differs from the October settlement

The press account describes a wider gap between the commission's approach and the October proposal than Duke's SEC filing does. Writing for Yahoo News on Nov. 17, Lily Carey reported that the commission's new large load tariff requires data centers to submit an upfront deposit covering the estimated cost of grid upgrades, including new power plants and transmission lines needed to serve them. Duke's 8-K does not use the words "upfront deposit." The fact sheet refers to a letter of credit for transmission network upgrades and a security posting tied to the stranded generation charge.

Carey's report contrasts the result with the proposal Duke and several technology companies put forward the prior month. That proposal would have required data centers to cover only the costs of connecting to the grid and would have applied an existing set of rates to all large customers. According to the report, the commission's rules instead create a separate set of rates for data centers. It also says the commission will set up a process for stakeholders to weigh in on how Duke determines the amount of infrastructure costs data centers pay.

The revenue side of the orders

The data center schedule was attached to a conventional rate decision. According to the 8-K, the approved settlements, filed July 17 for DEC and Aug. 5 for DEP, provide:

  • a 9.8% return on equity on a 53% equity component;
  • retail rate bases of about $25.7 billion for DEC and $17.8 billion for DEP;
  • about $3.8 billion (DEC) and $3.4 billion (DEP) of capital in the two-year multi-year rate plan;
  • an agreement to evaluate a one-year stay-out. Under it, neither utility would file a base rate case before Nov. 1, 2028, so long as the commission grants deferral of the cost of certain new generating assets.

The DEC fact sheet shows how far the request came down during the case. Duke's initial Nov. 20, 2025 request sought about $1,002 million, or 15.0%, over two years. Its June 19, 2026 rebuttal cut that to about $622 million, or 9.3%. The comprehensive settlement results in a $496 million revenue requirement over two years, which the fact sheet describes as an average annual rate increase of 3.7%, subject to finalization with the Public Staff. DEC also agreed to a $10 million shareholder contribution to bill assistance and home repair funds.

Duke said in the 8-K that DEC and DEP each expect one-time pre-tax accounting charges of $10 million in the fourth quarter of 2026.

For customer bills, securities.io reported average annual increases of 3.7% for DEC and about 3.4% for DEP. It put residential average annual increases at 4.8% (DEC) and 4.7% (DEP). For a household using 1,000 kWh a month, the outlet reported DEC bills rising $6.53 on Jan. 1, 2027 and another $4.66 on Jan. 1, 2028, and DEP bills rising $9.62 and then $5.89. Carey's report put household bill increases in Eastern North Carolina and the Asheville area at 9.3% over two years.

Why the details matter for developers and communities

Long contract terms, minimum billing demand, termination damages and security postings all address the same risk. A utility builds generation and transmission for a large customer, and that customer then shrinks its load or leaves before the costs are recovered. Securities.io reported that the commission itself said fixed costs could shift to existing ratepayers if expected demand fails to materialize or customers leave early. The contract terms and credit support in the schedule appear designed to put more of that risk on the data center customer rather than spreading it across the general rate base, at least in structure. How much it shifts in practice depends on the cost-allocation methodologies the fact sheet lists as still to be determined.

For utilities, local officials and residents near proposed campuses in Duke's North Carolina service territory, the schedule also defines which projects these terms reach. The 15-year minimum term in Duke's fact sheet is tied to data centers over 100 MW. The 8-K describes the schedule overall as applicable to "certain data center customers" and does not define that group further. Securities.io reported that the schedule applies to data-center customers with applicable demand of at least 50 megawatts.

What Happens Next

Duke's 8-K says revised rates are expected to take effect Jan. 1, 2027. Securities.io reports a second step in residential bills on Jan. 1, 2028. Duke has said it is still assessing the DC Schedule portion of the orders. According to Carey's report, the commission will set up a stakeholder process on how Duke determines data centers' infrastructure costs, and securities.io reports the orders direct a stakeholder process on standard methodologies for transmission-upgrade contributions and stranded-generation charges. The DEC fact sheet lists the methodologies for partial direct assignment of transmission upgrades and for the stranded generation charge as to be determined. None of the sources gives a schedule for that process. Separately, the stay-out the settlements commit Duke to evaluate would keep DEC and DEP from filing a new base rate case before Nov. 1, 2028, so long as the commission grants the requested deferral of new generating asset costs.