The Illinois General Assembly returns to Springfield on Tuesday, Nov. 17, for its fall veto session. Data center regulation is near the top of the agenda. The Chicago Sun-Times reported that the first week of the session is scheduled through Thursday, and that lawmakers then finish out their calendar Dec. 1 through Dec. 3. The paper also reported that Gov. JB Pritzker's top agenda item for the session is new data center regulation, while a Chicago Bears stadium bill is expected to take up much of the attention at the Capitol.

The main proposal is the POWER Act. The Sun-Times gives its full name as the Protecting Our Water, Energy and Ratepayers Act. The measure missed the spring session deadline. Since then, the governor has paused new state tax incentive agreements for data centers and has said lawmakers should pass reforms this fall.

What the POWER Act Would Do

The Sun-Times reported that the POWER Act would require data center developers to pay 100% of their costs before connecting to the grid. Capitol News Illinois described the bill's other main guardrails as water use reporting, community benefits agreements, and a requirement that data centers pay for their own energy from renewable sources. It also reported that the bill would require data center projects to track and report how much water they use and to submit water management plans to the Illinois Water Survey.

Pritzker described the bill earlier this month, as quoted by the Sun-Times. He said it would "require data centers to bring their own electricity with them — clean energy," and that it would also require the use of closed water systems. "It should be up to local communities, whether or not they want a data center," he said.

What the Bill Record Shows

Capitol News Illinois identifies House Bill 5513 as the POWER Act. A Feb. 12, 2026 archived copy of the General Assembly's bill status page shows the bill titled "Hyperscale Data Centers," filed Feb. 6, 2026 by Rep. Robyn Gabel, with Rep. Ann M. Williams added as chief co-sponsor. That snapshot is the version of the page this article could read, so it reflects the bill as introduced and not any later amendments or actions.

According to the synopsis "as introduced," the bill amends the Environmental Protection Act, the Energy Efficient Building Act, the Illinois Power Agency Act, the Public Utilities Act and related statutes. The synopsis lists these provisions:

  • Siting and community process: cumulative impact assessments, public notice and community benefits agreements, plus a prohibition on nondisclosure agreements.
  • New funds: a Data Center Community Intervenor Compensation Fund, and a Hyperscale Data Center Public Benefits and Affordability Fund funded by annual fees based on peak demand.
  • Water: water resource planning, quarterly water usage reporting, water scarcity plans, and Water Impact Permits with public hearings and renewal every five years.
  • Reporting to regulators: annual energy and water reporting to the Illinois Commerce Commission.
  • Energy procurement: expanded renewable energy procurement programs and a hyperscale data center self-direct program.

The sources do not say whether the veto session debate will use HB 5513, an amendment to another bill, or a new bill number, and the archived page does not show the bill's current status. Readers following a specific vote should check the General Assembly's site for the current bill number and text.

How the Bill Stalled in the Spring

Capitol News Illinois reported that conversations about the POWER Act were not over, but that the bill would not be ready by the General Assembly's May 31 deadline. Rep. Carol Ammons, who chairs the House Energy and Environment Committee and is a sponsor of the bill, said at a hearing that at least one more subject matter hearing was needed. She said she did not know when the bill might be considered, but that it could come up in the fall veto session after negotiations continue through the summer.

The Sun-Times described the bill as having "languished" at the end of May. Capitol News Illinois later reported that lawmakers had said negotiations would continue over the summer after the bill failed to pass.

The Tax Incentive Pause

The governor has also used his executive powers. Capitol News Illinois reported that Pritzker directed the Department of Commerce and Economic Opportunity (DCEO) to pause all new data center tax incentive agreements starting July 1. The incentives have been in place under bipartisan legislation signed in 2019. When he announced the pause, Pritzker called on lawmakers to pass comprehensive reforms during the veto session. According to the same report, he urged legislation that would require data centers to pay for the costs of their energy and water demand, support the generation of new renewable energy, track and report water use, adhere to air quality standards and enter agreements with host communities.

The two Capitol News Illinois reports describe the program's cost in slightly different terms. The report on the pause said 27 data centers benefited by more than $983 million from 2020 to 2024, citing a state report. The report on the stalled bill cited a 2024 report finding that at least 27 data centers had received incentives totaling $983 million in estimated lifetime tax breaks and benefits.

The pause applies to new agreements. The sources do not describe any change to agreements already signed.

Why It Matters Beyond Springfield

The proposals touch three groups that DataCenterFeed readers often follow: ratepayers, water users and host communities.

  • Utilities and ratepayers: Under the version the Sun-Times describes, developers would pay all of their costs before connecting to the grid. As introduced, HB 5513 would also charge annual fees based on peak demand to fund a public benefits and affordability fund.
  • Water: As introduced, HB 5513 would add quarterly water reporting and five-year Water Impact Permits with public hearings. Pritzker's comments about closed water systems address the same subject.
  • Local officials and residents: As introduced, the bill's community benefits agreements, ban on nondisclosure agreements, public notice rules and intervenor compensation fund all concern how host communities take part in siting. Pritzker framed the idea this way when he said the choice should be "up to local communities."
  • Developers: New state tax incentive agreements for data centers have been paused since July 1, according to Capitol News Illinois. Capitol News Illinois also reported that lawmakers heard warnings during hearings that onerous regulations might lead developers to pull projects from Illinois.

None of the sources reviewed for this article give a vote count, a committee hearing schedule, or a final bill text for the veto session.

What Happens Next

According to the Chicago Sun-Times, the veto session begins Tuesday, Nov. 17, and its first week is scheduled through Thursday, Nov. 19. Lawmakers finish out their calendar Dec. 1 through Dec. 3. Rep. Ammons said in the spring that the POWER Act could return in the fall veto session, and the governor has asked for comprehensive reform during it. No vote date for a data center bill has been reported in the sources reviewed.