A House bill introduced Nov. 11 would close two large categories of federal land to data center construction and add a condition to future federal land sales. If a parcel later becomes a data center site without Congress's approval, it goes back to public ownership.

The bill is H.R. 11002, the Protecting Our Public Lands from Data Centers Act of 2026. Rep. Maxine Dexter (OR-03) introduced it with 13 cosponsors, whom Data Center Dynamics describes as Democrats. It was referred to the House Committee on Natural Resources and also to the Committee on Agriculture. The sources reviewed show no committee action.

The text is short. What it covers, and what it leaves out, matters to developers looking at federal land, to land-management agencies, and to the communities near those lands. Here is a walk through it, based on the introduced text and the sponsor's description.

What does the bill actually prohibit?

The main provision is Section 2(b), and it is one sentence: "Notwithstanding any other provision of law, the construction of data centers on Federal land is prohibited."

Because it opens with "notwithstanding any other provision of law," the ban would override other statutes that could otherwise allow such construction. In its current form the bill sets no waiver process, no size threshold and no exemption by project type. The one route it leaves open applies to land conveyances, described below: a use specifically authorized by an Act of Congress.

Which land counts as "Federal land"?

The bill does not use the broad everyday meaning. It defines "Federal land" as two categories:

  • National Forest System land, which the Agriculture Department manages through the Forest Service. That explains the referral to the Agriculture Committee.
  • Land managed by the Secretary of the Interior.

The definition explicitly excludes Indian reservation lands, trust lands and other tribal lands. Federal property held by other agencies falls outside the bill's definition. Trade publication Data Center Dynamics described the measure as banning new data centers and related infrastructure on lands managed by the Forest Service and Interior. Its headline called the covered area "some federally-owned land."

The bill does not write its own definition of a data center. It adopts the one in Section 453(a) of the Energy Independence and Security Act of 2007.

What about land the government sells or transfers?

Section 2(c) deals with a different route to the same outcome. Any conveyance of federal land on or after the date of enactment would have to include a reversionary clause that takes effect if the land is used for a data center, unless an Act of Congress specifically authorizes that use.

Under this provision, a parcel that leaves federal ownership through a sale, exchange or other transfer stays tied to the restriction. Dexter's press release describes it as requiring lands sold or transferred to return to public ownership if used for a data center without congressional approval.

The bill text and the press release frame the scope a little differently. The release says the bill would prohibit the "development, sale or transfer" of covered federal lands nationwide for new data centers and related infrastructure. The statutory text bans construction outright in Section 2(b) and handles sales and transfers through the reversionary-clause requirement in Section 2(c). It does not ban conveyances themselves. The release is the sponsor's own description of the bill. The text is what would become law.

What has the sponsor said?

"Public lands belong in public hands and Oregonians must have a say before the federal government hands over millions of acres of public land managed by the Bureau of Land Management (BLM) for data centers," she said in the release.

The "millions of acres" figure comes from Dexter's statement. The bill text cites no acreage, and neither source identifies a specific BLM disposal or data center proposal by name or by number of acres.

Who has endorsed it?

Dexter's press release includes supporting quotes from the Center for Biological Diversity, the Sierra Club, Oregon Wild and Bark. The release and Data Center Dynamics both list the same nine endorsing groups:

  • Center for Biological Diversity
  • Sierra Club
  • Earthjustice Action
  • Save Our Wild Salmon
  • WaterWatch of Oregon
  • Bark
  • Oregon Wild
  • Columbia Riverkeeper
  • Oregon Data Center Defiance Coalition

Athan Manuel of the Sierra Club, quoted in both the release and Data Center Dynamics, thanked Dexter and Sen. Wyden for "standing up for our public lands." The sources reviewed for this article do not show a Senate companion bill.

Who are the cosponsors?

According to the introduced text, the 13 original cosponsors are Reps. Dean, Randall, Krishnamoorthi, Stansbury, Escobar, Kamlager-Dove, Grijalva, Scanlon, Goodlander, Pettersen, Ocasio-Cortez, Huffman and Min. Data Center Dynamics describes all 13 as Democrats.

What the bill does not do

Several points that readers will ask about are not covered by the introduced text, as summarized in the sources:

  • No source describes provisions affecting data centers already operating or permitted on covered land. The construction ban is written in the present tense, and the conveyance provision applies only to transfers on or after enactment.
  • The definition section in the sources does not separately address the transmission lines, substations or water infrastructure that serve a data center. The press release and Data Center Dynamics both describe the bill as reaching "related infrastructure," but that wording comes from their summaries, not from the provisions quoted above.
  • The bill sets no enforcement mechanism or penalty beyond the prohibition and the reversionary clause.

What Happens Next

H.R. 11002 has been referred to the House Committee on Natural Resources and, in addition, to the Committee on Agriculture. As of the sources reviewed, none of the sources reports a scheduled hearing or markup on the bill. The bill would need to clear committee and pass both chambers before any provision took effect. Section 2(c)'s reversionary-clause requirement would apply only to conveyances made on or after the date of enactment.