Hyperscale Data (NYSE American: GPUS) has put its plan for the Dowagiac, Michigan, campus in writing in more detail than before. In an investor-day presentation dated Nov. 23, 2026 and filed with the U.S. Securities and Exchange Commission as Exhibit 99.1, the company describes the site's conversion from bitcoin mining to AI colocation. The deck covers a signed customer, a construction budget, a funding plan that is only partly in place, and a local approval process the company says has started but not finished.

Three sets of numbers stand out: the size and timing of the first customer contract, the cost of building it and how that cost is being paid, and the much larger figure management has discussed for the site's eventual power. Each comes from the company's own filing, and several depend on conditions the company lists alongside them.

The Contract: 20 MW in Two Phases

According to the presentation, a California-based neocloud customer has contracted for 20 MW of colocation capacity at the Dowagiac campus. The company describes two 10-MW deliveries: the first in December 2026 and a second 10 MW by March 31, 2027. The presentation calls both dates management targets.

The deck also describes what happens if those targets slip. Under the master services agreement terms it summarizes, qualifying utility, permitting and customer delays extend a target date day for day. The customer can receive service credits against recurring charges if delivery runs more than 90 days past the adjusted target, and it gains a termination right for an affected phase after specified delays, subject to notice and a chance for the company to complete the work. The filing does not state the adjusted target dates.

The company says bitcoin mining at the Michigan site stopped on Sept. 1 as the facility shifted toward AI hosting.

On potential revenue, the presentation puts the 20 MW contract at about $1.2 billion over a term of up to 20 years. It says the figure would be about $3.0 billion if the customer takes an additional 32 MW, for 52 MW in total. These are the company's own estimates of contract value under stated assumptions. They are not reported revenue, and the filing does not say the customer has committed to the added capacity.

The Money: $121.1 Million, Partly Funded

The presentation puts the initial 20 MW buildout at $121.1 million. As of Nov. 20, 2026, the company says, $70.9 million of that had been incurred and $53.8 million paid.

The deck lists the following funding raised or received to date (amounts approximate):

  • $74.4 million in gross bitcoin sales proceeds, which the deck says also fund debt repayment as well as the Michigan work
  • a $15.0 million convertible note (gross, across the Nov. 6 initial closing and a second closing)
  • $13.7 million in non-recurring charges (NRCs) paid by the customer
  • a $5.6 million cash security deposit

Project-level debt has not been raised. The company says it has engaged Newmark to find lenders for that financing, and that no funds have been committed and terms are open.

The presentation also says that in September, management set $750 million as the threshold for considering a sale, which it described as its own assessment without an independent appraisal. DataCenterFeed draws no conclusion from it about the company's plans.

340 MW: A Number With Conditions Attached

The larger number tied to Dowagiac is not new. In April, ABC57 reported that Hyperscale Data and its subsidiary Alliance Cloud Services had announced in July 2025 that they intended to expand the existing data center from 50 MW to 340 MW. In March 2026, the companies announced an agreement to buy 48.5 acres, ABC57 reported. WVPE described the same deal on March 31 as Alliance Cloud Services agreeing to buy nearly 50 acres for the data center on Prairie Ronde Street.

The new investor deck repeats the figure more cautiously. It says management has discussed about 340 MW of potential gross power, and that this is subject to utility agreements, approvals, capital and demand. The filing does not describe a signed utility agreement for that capacity. Readers in Dowagiac and Cass County should treat the 340 MW figure as a stated ambition with conditions attached, not a permitted or contracted load.

The Local Record: A Push for Information

The project's relationship with the city has been strained. When the land purchase was announced in March, Mayor Patrick Bakeman told WVPE that city administration learned of the plans from the company's press release and had asked the company for information.

By mid-April, the city had gone further. ABC57 reported that Dowagiac issued an open letter to the company's CEO demanding information about the project. The chairman of the Pokagon Band of Potawatomi publicly supported the city's push for transparency, according to the same report.

The investor deck gives the company's account of what has happened since. It says the city accepted a complete site-plan application on Nov. 6. It says city staff confirmed on Nov. 16 that an administrative review of sound, stormwater and fire safety was underway. And it says the city told the company it would post a status update by Nov. 23. The presentation says the city's Nov. 16 notice left the decision open.

The city's own public pages do not yet confirm that timeline. The Building & Planning office page describes the office's role: it administers the zoning ordinance, compiles Planning Commission agendas, serves as Planning Administrator, and is located at City Hall, 241 S. Front Street. It does not post the November site-plan status. The Nov. 6 and Nov. 16 dates above come from Hyperscale Data's filing, not from a city document.

What It Adds Up To

The filing gives a more specific picture of the Dowagiac conversion than earlier announcements. It names a customer type and a contracted load, sets delivery targets, states a budget with amounts already spent, and lists the funding in hand. It also shows what is still unresolved: project debt is not committed, the delivery dates are management targets, with service credits and termination rights in the contract for long delays, and the city's site-plan review was still open as of the deck's date. The 340 MW figure that drew attention in 2025 now appears with explicit conditions on utility agreements, approvals, capital and demand.

What Happens Next

According to Hyperscale Data's presentation, the City of Dowagiac said it would post a status update on the site-plan review by Nov. 23, 2026. The company says the administrative review covers sound, stormwater and fire safety, and that its Nov. 16 notice left the decision open. Matters that go to the Planning Commission are placed on its agenda by the city's Building & Planning office at City Hall, 241 S. Front Street. As of publication, the city's Building & Planning page did not show the update.

On the construction side, the company's management target for the first 10 MW of customer capacity is December 2026, with a further 10 MW targeted by March 31, 2027. The company says it is still working with Newmark on project financing, with no funds committed so far.