Consumer advocates from seven states in the PJM Interconnection have asked the grid operator's board to postpone its next capacity auction. The auction for the 2029/30 delivery year is scheduled for Dec. 9-15. The advocates want it held back until data center load, which they describe as "both real and speculative," is taken out of the load forecast and handled through a separate procurement.
Utility Dive reported that the advocates sent the letter on Wednesday, Nov. 18. The signers are the Ohio Consumers' Counsel, the Delaware Public Advocate, the West Virginia Consumer Advocate, the Maryland Office of People's Counsel, the Pennsylvania Office of Consumer Advocate, the New Jersey Division of Rate Counsel, the Illinois Attorney General's Office and the Illinois Citizens Utility Board. They asked PJM's board to answer in writing by Nov. 23.
PJM has said it does not support a delay. Spokesman Jeffrey Shields told Utility Dive that the auction includes an established price cap. He said postponing it "could destabilize the market and increase the risk of power interruptions."
What the advocates are asking for
The letter makes two requests. First, it asks PJM to postpone the 2029/30 Base Residual Auction (BRA) until data center loads are removed from the load forecast the auction relies on. Second, it asks PJM to hold a separate reliability backstop procurement for those large loads, according to Utility Dive.
The advocates also point to a statement of principles that PJM and 13 governors issued in January. That statement said forecasts of large new loads should be "real and verified," Utility Dive reported. The letter argues that the forecast behind the December auction does not meet that standard.
A postponement is not something PJM's board can order by itself. Utility Dive reported that any delay would need approval from the Federal Energy Regulatory Commission.
The market monitor's numbers
The letter relies on the Q3 2026 State of the Market report from Monitoring Analytics, PJM's independent market monitor. Utility Dive dated that report Nov. 12. It covers January through September.
The report's executive summary says data center load has caused an "irreversible increase of $29.4 billion in capacity market costs" so far. The monitor puts the combined increase from data center load (actual and forecast) across four auctions at $29,368,774,465. Those auctions are the 2025/26, 2026/27, 2027/28 and 2028/29 BRAs.
For the coming auction, the monitor points to PJM's Reliability Backstop Procurement filing. The report says that filing is "now delayed until after the December BRA," which leaves most forecast data center load inside the 2029/30 auction. In the monitor's words, that "effectively ensures that the auction will clear at the maximum price and add another $5 to $10 billion."
The report also says the 2029/30 BRA uses PJM's 2026 load forecast. According to the monitor, that forecast includes data centers that have already been canceled or are unlikely to reach their projected levels. Utility Dive summarized the monitor's position this way: canceled or unlikely data centers could add $5 billion to $10 billion in costs for PJM's 67 million consumers.
The advocates' request closely follows the monitor's own recommendation. The report states: "PJM should postpone the December auction until it can remove all forecast data center load from the auction, and run a reliability backstop auction for all data center load that wants to interconnect and does not have a bilateral contract for generation."
What PJM's own parameters show
PJM published the planning parameters for the 2029/30 auction on Sept. 3. The document reflects figures posted Aug. 31. It sets out how much capacity the auction is meant to buy and the price limits.
- Forecast peak load: PJM puts the RTO-wide forecast peak for 2029/30 at 171,916 MW. That is up 3.6% from 165,954 MW for 2028/29.
- Reliability Requirement: PJM lists 158,712 MW, an increase of 2,699 MW, or 1.7%.
- Price collar: The cap is $337.83/MW-day and the floor is $181.91/MW-day, in unforced-capacity (UCAP) terms. Both were set under FERC Docket ER26-1556.
The parameters also show load growth changing the auction's internal map. PJM says it added PJM WEST as a separately modeled Locational Deliverability Area (LDA). The reason given is that the area's import capability ratio (CETL/CETO) fell below 115% because of large forecast peak load growth. The document also lists the DOM and COMED zones with CETL/CETO ratios below 1. In those zones, the forecast need to import capacity exceeds the transmission system's modeled ability to bring it in.
The two sides are reading the same cap differently. PJM's spokesman cites the established price cap as a protection for consumers. The market monitor says the forecast data center load effectively ensures the auction will clear at that maximum.
Why the timing matters
The letter arrived less than four weeks before bidding opens. Utility Dive reported that the advocates noted PJM planned to publish final planning parameters on Nov. 19, the day after the letter was sent, and that those parameters may remove canceled or delayed data center projects from the auction's demand curve.
That timing is central to PJM's response. Shields said a postponement this close to the auction could destabilize the market and raise the risk of power interruptions. The advocates and the market monitor argue that running the auction on the current forecast locks in costs that cannot be undone. The monitor describes the $29.4 billion already incurred as "irreversible."
This is not the only challenge to how the auction is run. Utility Dive noted that Exelon filed a complaint at FERC on Nov. 3 challenging PJM's three-year forward auction, partly over the uncertainty in forecasting data center load.
What Happens Next
According to Utility Dive, PJM planned to publish final planning parameters for the 2029/30 Base Residual Auction on Nov. 19. The advocates asked PJM's board for a written response by Nov. 23. The auction is scheduled for Dec. 9-15. If PJM decided to postpone it, FERC would have to approve the delay.